Ford’s October proposal distinguishes isolated backup and charging from operating an electric truck in parallel with the grid. The 2027 Fathom is designed with an onboard inverter.

Ford’s illustration of a bidirectional charger beside a garage door
Ford’s illustration of a bidirectional charger beside a garage door. Source image.

Ford outlined a plan on October 27 to simplify utility approvals for two-way charging on its forthcoming Fathom electric pickup. The company says American Electric Power, BC Hydro, Consumers Energy, Exelon and Pacific Gas and Electric joined a working group formed in July 2026. It wants utilities to distinguish vehicles that only charge or provide isolated backup power from those that send power while connected in parallel with the grid.

The product change is an inverter built into the truck. Battery packs supply direct current, while homes use alternating current. Previous systems relied on separate equipment mounted at the home to convert the flow. Ford says Fathom will be able to supply more than a projected 10 kW of alternating-current power without a separate wall-mounted inverter. It expects the 2027 model to start under $30,000 and says the design is intended to meet applicable UL 1741 requirements and comply with the IEEE 1547 interconnection standard.

Ford describes two home uses with different hardware. For home energy management, a customer could charge the truck when rates are low and run part of a home's load from its battery when power costs more. Ford expects the Home Power Station needed for this mode to cost about half as much as its first-generation bidirectional charger. Backup during an outage would also require Ford’s home backup panel. Ford projects that its backup hardware will cost at least 60% less than its earlier equipment. These are comparisons with its own systems, with no local installation price in the October disclosure.

The utility group is tackling a separate problem. Ford said that interconnection processes were mostly written for stationary equipment, including rooftop solar and batteries. The group proposes reserving interconnection for operation in parallel with the grid. Under that distinction, a truck used for charging or isolated backup would not require the same process. The group’s proposal would still need to be applied by utilities and regulators. Ford’s product footnotes say home energy management requires the Home Power Station, utility approval and an active Ford trial or plan. Backup may also require notice or approval.

For customers choosing equipment, the question is which use they want and which utility rules apply at their address. For utilities, the same pickup and charging hardware may support different uses, so the application process needs to identify whether the system can export in parallel. The October announcement sets out the group’s approach before the Fathom launches. It does not announce nationwide approval or electricity savings for specific customers.