CATL and Seres plan 10–12 GWh battery expansion inside Chongqing vehicle plant
The second phase would take combined annual capacity above 20 GWh. An October agreement also extends CATL’s battery supply across the AITO vehicle range.

CATL and Seres plan to add 10 to 12 GWh of annual battery capacity inside the Seres Super Factory in Chongqing. The proposed second phase would bring combined annual capacity at the site above 20 GWh when complete, CATL said on October 10. The expansion is part of a long-term agreement signed in Chongqing that extends the battery supplier’s coverage across the AITO vehicle range.
This is an expansion of an existing manufacturing arrangement. In June 2025 CATL started operating two of its cell-to-pack production lines within the Seres factory. CATL said the site was its first production base in Chongqing and the first use of its embedded manufacturing model, under which a supplier builds packs at the customer’s vehicle plant. The lines started out making battery systems locally for AITO vehicles. The October agreement advances a second phase on the same site, where adding pack capacity can support vehicle assembly without a separate long-distance haul for the finished pack.
The figures CATL disclosed are annual capacity targets, which measure the energy content of the output the plant is designed to produce. They do not fix an equivalent number of vehicles. AITO can use different pack sizes across its vehicles, and actual production will depend on the mix and how fully the lines run. CATL gave no commissioning date, phase-two investment sum or named allocation of the new capacity by vehicle model in the signing release.
CATL said AITO has used its batteries across the range since the brand’s launch. AITO had passed 1.2 million cumulative vehicle deliveries by the time of the announcement, according to the supplier. That is a lifetime brand figure. It is separate from the number of packs produced at the embedded facility, which opened in 2025. The planned addition therefore expands a local system that came after the original supply relationship was already in place.
The agreement also outlines cooperation on fast-charging infrastructure and battery services throughout the product life cycle. The companies named Europe, the Middle East and Central Asia as markets they intend to pursue together. That gives the deal a service and distribution component beyond the project in Chongqing. The named regions are a statement of intent. The companies gave no dates, launch-market sequence or commitment to export packs from the expanded plant in the October announcement.